- $48M 117,000 GFA multi-use facility including lecture
theatres, classrooms, café, faculty offices and 400 space
underground parking structure;
- OPM was retained by the University of Toronto to manage the Project throughout the Pre-construction, Construction and Post Construction phases of the Project;
- To expedite the Project schedule, OPM separated the Project into
its two significant entities – the parking garage and the
main building permitting construction to begin on the foundations
and parking garage while the construction documents were being
completed for the main building;
- This necessitated separate tendering of the two phases and separate
general contracts. The handoff from the parking garage contractor
to the building contractor occurred on schedule;
- The Project was completed within schedule and budget.
|
|