- $48M 117,000 sq. ft. multi-use high tech facility including lecture
theatres, classrooms, café, faculty offices and 400 space
underground parking structure;
- Retained by the University of Toronto to manage the Project from
the outset, OPM has managed all user committees and related functional
programming, the design process, value analysis, budgeting, the
general contractor tendering process and construction activity;
- To expedite the Project schedule, OPM separated the Project into
its two significant entities – the parking garage and the
main building permitting construction to begin on the foundations
and parking garage while the construction documents were being
completed for the main building;
- This necessitated separate tendering of the two phases and separate
general contracts. The handoff from the parking garage contractor
to the building contractor occurred on schedule;
- The parking garage is now complete and the main building is under
construction with both phases of the project on budget and on schedule.
|
|