- Construction of a $15M 40,000sq. ft. science building incorporating
new research labs, faculty offices, teaching labs, lecture halls
and classrooms;
- Project scope also includes partial renovation of the existing
Science Complex as space vacated by uses moving into the new facilities
are backfilled with other faculty uses;
- This new high level teaching and research facility is arrayed
around a central meeting place and creates a strong public link
between the Science Complex and the Environmental Science Building;
- OPM was retained by Trent University as Project Manager at the
commencement of Construction Phase to rectify significant budget
and schedule control problems;
- The complexity of base building design has resulted in difficulty
in the general contractor’s implementation of the project;
- In conjunction with the Project Team, OPM has developed necessary
contingency planning to meet project schedule and budget expectations.
|
|