- $26.5 million LEED Certified, multifunctional facility including a double gymnasium, eight lane pool, aquatic fitness facility, fitness and free weight room, locker rooms, sports medicine clinic and administrative offices;
- OPM was retained by the University of Toronto to oversee the construction and post construction phases of the project to ensure that the budget and schedule objectives were achieved with occupancy available for the 2006-2007 academic year;
- Restrictive site conditions and access problems due to the projects central campus location necessitated close coordination between the project manager and construction manager to ensure the safety of all on campus and to minimize disruption to ongoing campus activities;
- The project was successfully completed on schedule and budget.
|
|